DEVELOPMENT DIVISION APARTMENT OVERVIEW

Denis Hickey, CEO Development Division



- Development Division Strategy $\blacksquare$
- Apartments Strategy $\blacksquare$
- Projects Overview $\blacksquare$
- Question and Answer $\blacksquare$
- Drinks $\blacksquare$
Core Business Activities

% Gross Assets
As at 31 Dec 2003 $9%$ 73% 18% Benchmark $5 - 10%$ 65-75% 20-25%
Strategic Direction - Apartments
BUSINESS CASE
- Growing sector in the Residential Market $\blacksquare$
- Incremental growth for the Division $\blacksquare$
- Strong synergies with our Residential Estates operation $\blacksquare$
- Future trend will be mixed use developments $\blacksquare$
FRAMEWORK
- Establish this as a "National" business $\blacksquare$
- Focus on discerning purchasers (value, quality, design) $\blacksquare$
Strategic Direction - Apartments
FINANCIAL TARGETS
- Target to make a 15% net profit before tax $\blacksquare$
- 1H04 results reflected general business establishment / overhead $\blacksquare$ costs
- Anticipate achieving target in FY06 $\blacksquare$
APARTMENTS

Hugh Martin - General Manager


STRATEGY
- Building a Business $\blacksquare$
- National Structure $\blacksquare$
- Market Segment $\blacksquare$
Business Strategy

There are 3 key areas where significant "value added" is generated

TEAM
Internal experienced skilled resources $\blacksquare$



SOUTHBANK

Location Corner of Grey & Glenelg Streets South Bank, QLD
Planning Status
DA Approved - August 2003
Forecast Completion Date
September 2005
WEST END
Pigeon Close View

Location Beesley Street West End, QLD
Planning Status
DA Approved - March 2004
Forecast Completion Date
Late 2005
Riverside Drive View

RIVERSIDE DRIVE BUILDING
NORMAN PARK

Location 90 - 94 Wynnum Road Norman Park, QLD
Planning Status
DA forecast to be Submitted - May 2004
Forecast Completion Date
Late 2007
ABODE

Location 599 Pacific Highway St Leonards, NSW
Planning Status
DA Approved - November 2000
Completion Date
February 2004
BALGOWLAH VILLAGE

Location
Bounded by Sydney Road, Condamine, Woodland and Griffiths Streets Balgowlah, NSW
Planning Status
DA Submitted - December 2003 DA Approval - June 2004
Forecast Completion Date Early 2007
GORDON
McIntyre Street View

Merriwa Street View

Location
Merriwa & McIntyre Streets Gordon, NSW
Planning Status
DA Forecast to be Submitted - April 2004
Forecast Completion Date
Stage 1 Forecast: June 2006


Location East Lake Parade Kingston, ACT
Planning Status DA to be Submitted - May 2004
Forecast Completion Date February 2006

- Clear strategic plan $\blacksquare$
- Proven capabilities $\blacksquare$
- Risk Management / Pro-active Capital Management $\blacksquare$
- Confident of delivery $\blacksquare$
Disclaimer
Corporation/ Responsible Entity
Stockland Corporation Limited ACN 000 181 733 Stockland Trust Management Limited ACN 001 900 741 AFSL No. 241190 16th Floor 157 Liverpool Street SYDNEY NSW 2000
Disclaimer of Liability:
While every effort is made to provide accurate and complete information, Stockland does not warrant or represent that the information in this presentation is free from errors or omissions or is suitable for your intended u excluded, Stockland accepts no responsibility for any loss, damage, cost or expense (whether direct or indirect) incurred by you as a result of any error, omission or misrepresentation in information in this presentation. without notice.